September 1, 2000. Trim is mostly done around all sides, and shingles are well started.
(big... huge... print)
 
September 1, 2000. Note the trim along the top edge.
(big... huge... print)
 
September 1, 2000. Trim complete on west side too.
(big... huge... print)
 
September 5, 2000. They finished the roof, put on some Tyvek, and added some temporary stairs so they could access the second floor without going through the current house.
(big... huge... print)
 
September 18, 2000. East wall. Not all the siding was delivered yet, so it's not quite done.
(big... huge... print)
 
September 18, 2000. North wall almost complete.
(big... huge... print)
 
September 18, 2000. West wall partially complete.
(big... huge... print)
 
September 25. West wall completed several days ago. Looks like a house!
(big... huge... print)
 
September 25, 2000. North and west walls mostly complete.
(big... huge... print)
 
September 25, 2000. East wall. No progress here.
(big... huge... print)
 
October 14, 2000. Almost all the siding is done now. Chimney added.
(big... huge... print)
 
October 14, 2000. An essentially complete view of the house from the southwest.
(big... huge... print)
 
November 17, 2000. Outside cleaned and graded. Gutters installed November 13.
(big... huge... print)
 
November 17, 2000. Outside cleaned and graded. Gutters installed November 13.
(big... huge... print)
 
November 17, 2000. New steps installed.
(big... huge... print)
 
December 14, 2000. First snowfall.
(big... huge... print)
 
DESCRIPTION: Winter 2001. A view of our nearly complete house.
(big... huge... print)
 
DESCRIPTION: Winter 2001. A view past our house to the river.