New boatshed.
May 6, holes dug.
|
New boatshed.
May 8, supports poured.
|
New boatshed.
May 12, floor system started.
|
New boatshed.
May 14, floor system complete.
|
New boatshed.
May 17, floor complete.
|
New boatshed.
May 18, walls begin.
|
New boatshed.
May 21, walls nearly ready.
|
New boatshed.
May 21, view from the water's edge.
|
New boatshed.
May 25, walls complete, roof started.
|
New boatshed.
May 29, roof complete.
|
New boatshed.
May 31, sheathing complete.
|
|
July 7, 2007. After a three-week vacation we find the boathouse very far along; roofing, some siding, windows and doors, and electric and water.
|
July 7, 2007. Path of the underground water and electric line, from house to boatshed.
|
July 7, 2007. Path of the underground water and electric line, from house to boatshed.
|
July 7, 2007. Path of the underground water and electric line, from house to boatshed.
|
July 7, 2007. Path of the underground water and electric line, from house to boatshed.
|
July 13, 2007. One of the two "barn" doors, and some more siding. This is the southwest corner.
|
July 13, 2007. One of the two "barn" doors. This is the west side.
|
September 8, 2007, mostly done!
|
September 8, 2007... the north side has a tractor ramp.
|
October 10, 2007.
The boatshed is done! Painting done, faucet and water fountain installed.
|
October 10, 2007.
A view from the boatshed at the boatrack and the new dock.
|