IMGP3185.JPG
August 13, We begin to work on the retaining walls to be built near the house. This means digging trenches! Note the white pipe in the lower left, which is connected to the downspout for the roof and eventually empties far out in the yard.
IMGP3186.JPG
August 13, for the record, the roof drain comes down from the gutters, under the steps, and is visible here in the white drainage pipe -- now buried under the wall.
IMGP3183.JPG
August 13, the other side of the wall after compacting sand and base material.
IMGP3188.JPG
August 17, Mara shows that we finished most of the north wall section.
IMGP3190.JPG
August 17, Mara shows that we finished most of the south wall section. We line with landscape cloth to keep sand and dirt from leaking through the wall.
IMGP3192.JPG
August 17, I note where the electric lines for the generator pass through the bottom layer of the wall... note the missing block.
IMGP3194.JPG
August 17, we line the inside of the wall to prevent sand and dirt from leaking, after laying a bit of sand along the bottom of the wall.
IMGP3196.JPG
August 20. The wall is finished after gluing the cap blocks into place, and now we start the backfill using another truckload of topsoil. The north wall has some scraps of pavers and wall blocks under all the soil, as fill.
IMGP3195.JPG
August 20, the south wall is done and backfilled; Pam starts to lay the landscape cloth on top.
IMGP3201.JPG
August 20, the north wall is done and backfilled.
IMGP3198.JPG
August 20, we start to add more dirt to the low area between the patio and garage; and along edges of the patio.
IMGP3199.JPG
August 20, we remove excess sand from the main patio; Andy used his little truck and Pam used the wheelbarrow. The wagon holds a load of dirt for backfill.
IMGP3202.JPG
August 21, a belated picture of the final section of the patio, which was finished the weekend before. Pam did some fancy cutting and fitting to merge the walkway into the patio. The sand is wet so it looks a bit messy.
IMGP3203.JPG
August 21, the walkway and south wall are all done, complete with mulch!
IMGP3204.JPG
August 21, we've finished the dirt fill in this area and laid as much cloth and mulch as we have available.
IMGP3205.JPG
August 21, the north wall is done and mulched.
IMGP3441.JPG
September 4. Andy demonstrates the wall as a bench.
IMGP3442.JPG
September 4, time to spread mulch.
IMGP3444.JPG
September 4, time to spread mulch.
IMGP3443.JPG
September 4. Two weeks ago John and Daddy built this little wall along the base of the generator shed.
IMGP3445.JPG
September 4, mulch and edging are nearly complete, and a few of the new plants are ready for planting.
IMGP3446.JPG
September 4, the mulch is nearly complete.
IMGP3447.JPG
September 5. With the last of the mulch, the patio is done! Andy demonstrates.
IMGP3449.JPG
September 5. With the last of the mulch, the patio is done! Andy demonstrates.