Phase 1: Foundation and first-floor deck
Click on a photo for a bigger image.
July

The frame is nearly finished being cut in the factory at the
Davis Frame Company,
and waits in their warehouse until delivery.
Tuesday August 5 (approx)

The foundation forms are in place, and the concrete is poured.
Thursday August 7 (approx)

The completed foundation.

Adding rigid foam insulation to the frost wall under the walk-out wall.
Friday August 8 (approx)

Under the basement floor: rigid foam insulation, and then sand on top of that.
Tuesday August 12 (approx)

Framing the walk-out basement wall.

The septic system leach field.
Friday August 15

The basement walk-out wall and the first-floor deck are complete.
Ready to start erecting the frame.

The timber frame was delivered today (under the
tarps), along with the siding and the shingles.
Go to Phase 2: Timber frame erection