Phase 3: Wall and roof panels
Phase 4: Siding, roofing, internal work
Click on a photo for a bigger image.
October 3

Here's a picture of the Category 5 network cable coming up
through an internal wall. I decided to run several Cat5 network
cables to every room, for phone and computer networks of the
future....

Meanwhile, Pam started installing the R11 insulation in all the
interior walls, for soundproofing. Unpleasant job!

Drilling the well...

And the siding started to go on the outside.
Approx October 13

Siding done on the road side.
Approx October 16

Siding complete on the River side too.
October 17

A view of the house from the middle of the Connecticut River.
Late October

A view of the outside, with completed driveway.