8/12. John and Mara adjust the gravel under the steps to better align them.
|
8/12. John and Mara adjust the front steps until they are level.
|
8/13 start; yesterday we got the second wall started and completed the drainage piping for the third.
|
8/13 start; Two layers done on two walls, and third ready to start.
|
8/13 end; three walls complete, waiting for steps and caps.
|
8/13 end; three walls complete, waiting for steps and caps.
|
8/20, our first rainy workday. Yesterday, David used the tarps to build the lower wall under cover.
|
8/20. Pam starts to cut and lay wall caps, and to build steps.
|
8/21 start; yesterday we capped and backfilled all the walls, removed excess dirt, and graded the land around.
|
8/21 start; we finished all the walls yesterday, including caps. Started the steps.
|
8/21 start; yesterday we put wall caps on all four walls!
|
8/22 start; yesterday we made more progress on steps.
|
9/7 end (after a vacation and other time away from the job); Pam has finished the steps, mostly, and begun plantings. All the excess dirt removed.
|
9/7 end; the steps are looking great!
|
9/7 end; I added a little detail with these blocks to hold back the stones between walkway and house.
|
9/10. The steps are very nearly complete, and the shower pad is in place.
|
9/10. The steps are very nearly complete, and the walkway is ready for sand.
|
9/10. The pad for the shower is set. The green edging starts here, and will soon surround the whole project.
|
9/17. The steps are all done and the lower stone walk is laid.
|
9/17. Andy and John enjoy some lemonade on a hot sunny day.
|
9/17. An auxiliary project - using the sand and stones removed from the old walkway to finally pave the entryway to the walkout basement.
|
9/24 start; yesterday we edged and mulched the whole area, after laying fabric under parts of it.
|
October 10, 2006. The walls project is complete!
|
October 10, 2006. The walls project is complete!
|
October 10, 2006. The walls project is complete!
|